Luke Lu
Tarun Sanghi, PhD, CFA
Robin Marshall, MA, MPhil,
Tajinder Dhillon, CFA,
Executive Summary
Debt financing has become a primary driver of the artificial intelligence (AI) and data centre infrastructure boom. Major technology companies and specialised developers have moved from self-funding through cash flow to borrowing hundreds of billions of dollars, with total AI-related debt issuance exceeding $500 billion in 2026. Hyperscalers are now projected to debt-finance roughly one-third of their massive capital expenditure, as spending begins to outpace operating cash flows.
Major financing structures include unsecured corporate bonds (mostly long-dated investment-grade corporate bonds issued by big tech to fund enterprise-wide compute and data centres), off-balance-sheet special purpose vehicles (SPVs), private credit funds, and securitisation (through ABS and CMBS on secured lease cash flows and properties).
Rising AI concern amid a shifting political landscape
As concerns grew recently regarding soaring AI spending and questionable payoff prospects, data centre debt has seen bond yields and credit default swap (CDS) spreads surging. Investors are having digestion issues due to name concentration risk. Capital markets are starting to show signs of fatigue with a dramatic slowdown of data centre debt issuance in the last two months. Banks have been pulling back from AI lending, and Wall Street is cutting exposure.
AI fears have accelerated following the Democrats’ midterm sweep, which could lead to heightened regulatory oversight on AI deployment, and moratoriums or tighter restrictions on data centre construction in many states and localities. With Fed rate rises expected on the horizon, data centre debt is facing a severe test against rising borrowing costs, a political backlash, local energy/permitting delays, and asset depreciation.
Data centre financing is part of a major shift in the US investment/savings balance
A surge in demand for capital and corporate issuance in both public and private credit deals, has placed upward pressure on rates. In the US public debt market, hyperscaler issuance has now surged to about 15% of total IG credit issued YTD[note1]. This comes when the US government is also borrowing to finance substantial budget deficits – the latest official estimate for fiscal 2025-26 is $2 trillion[note2], approx. 6% of GDP. With a low household savings ratio of only 3.8% of disposable income[note3], this has tilted the US investment/savings balance strongly towards excess investment, in contrast to the era of secular stagnation between 2008 and 2021.
Data centre financing deals also tend to be longer-duration fixed rate finance, to match the cash flows from the underlying assets, so other things equal, it will impact longer rates more than short and steepen the yield curve somewhat. Treasury issuance has dried up in longs particularly and is heavily skewed towards shorts and T-bills, which at least creates more room for IG borrowers.
US capex surge based on demand projections creates overbuild & recession risks
But the surge in capex in A and data centres could create overbuild and cyclical economic risks, since much of the build-out is based on projected demand, rather than realised demand for AI. One possible scenario is a recession risk, should it become clear there is a significant excess capacity problem. This is quite typical of an infrastructure build-out, like the railroads in the 19th century, Japanese property in the 1990s, global Telecoms boom in the early-2000s, and Chinese real estate crash in the 2010s. Potential consequences include deals going sour, a de-rating of the equity sectors involved, some corporate failures and sizeable employment losses if a recession transpires.
Another Global Financial Crisis (GFC) lesson was higher cross correlation of returns than expected
Cross correlation of returns in different asset classes may also prove to be much higher than expected, and near 1 in a major risk-off event, like the GFC or Covid. In that regard, the impact of a major AI slowdown could impact a range of sectors, from electrical utilities to semi-conductor manufacturers, to electrical equipment manufacturers, to construction to industrial REITs.
But systemic risks appear low, despite some evidence of circular AI financing
There is also some evidence of complex and circular financial engineering here – which we outline in the note - Mapping circular financing in AI: Does it add instability?. This raises the question of systemic risks, with deals leveraged on the same underlying cash flows and whether another sub-prime Mortgage Backed Securities (MBS) crisis is developing. Complex derivative chains, often backed by the same underlying cash flows in sub-prime mortgages, are not evident in the public domain at least, and bank involvement in AI financing is still relatively limited versus the subprime crisis.
Hyperscalers, Neoclouds, and AI infrastructure companies
The AI infrastructure buildout is increasingly a competitive necessity, but the financial trade-offs are becoming harder to ignore. Across the ecosystem, unprecedented capex is eroding free cash flow, increasing reliance on external financing and placing greater scrutiny on earnings quality and credit risk.
In this section, we examine the debt and equity financing of hyperscalers, neoclouds, and AI infrastructure companies to assess how they are funding their growing capital expenditure and the implications for their balance sheets.
Six major hyperscalers—Alphabet, Amazon, Alibaba, Meta, Microsoft and Oracle—are forecast to spend more than $1 trillion annually on capex from 2027 through 2030, according to StarMine SmartEstimates. Spending has grown at an annualised rate of nearly 50% since the launch of ChatGPT in 2022, driven by investment in chips, servers, and data centre capacity. Annualised growth is expected to moderate to 2.6% annually through 2030, albeit from a much higher base.
Our neocloud cohort—CoreWeave, Nebius, IREN and WhiteFiber—comprises specialised providers of ‘computing as a service’ for AI workloads. The group is forecast to spend $96 billion in 2027, roughly one-tenth of our hyperscaler cohort and more than three times that of our AI infrastructure cohort, comprising of Applied Digital, Core Scientific, TeraWulf, Cipher Digital, Hut 8, Equinix and Digital Realty, which provide physical infrastructure supporting AI computing.
Elevated Capex to Cash Flow ratio
The pace of investment has raised investor concerns, with all three cohorts expected to generate negative free cash flow (FCF) from 2026 through 2028. As an example, hyperscaler FCF is forecast to swing from a $209 billion surplus in 2025 to a $189 billion deficit in 2027—a deterioration of nearly $400 billion in two years.
Exhibit 1 shows the Capex to Cash Flow ratio for the three cohorts. It can be observed that hyperscalers are expected to spend nearly all their cash flow from operations (CFO) on capex in 2026, compared with a historical average of 40%. The ratio is expected to peak near 115% in 2027 before easing modestly in subsequent years. In contrast, neoclouds and AI infrastructure cohorts are expected to spend more than three times their CFO on capex in both 2026 and 2027, reflecting the upfront investment required to build AI compute capacity.
Exhibit 1: Capex to CFO Ratio (%)
Source: LSEG Workspace, LSEG StarMine. Past performance is not a guide to future returns. Please see the end for important legal disclosures.
| Fiscal year | Hyperscalers | Neoclouds | AI infrastructure |
|---|---|---|---|
| FY2026 | 100% | 365% | 290% |
| FY2027 | 115% | 340% | 320% |
| FY2028 | 100% | 265% | 220% |
| FY2029 | 80% | 490% | 210% |
Debt vs. equity financing
The strain on FCF has prompted hyperscalers to increasingly tap bond and equity markets to finance their expansion plans. Year-to-date, the hyperscaler cohort has raised $279 billion in gross bond issuance/proceeds and $162 billion in gross equity offerings (Exhibits 2 and 3). Bond issuance alone is already 2.6 times the amount recorded in all of 2025, with Amazon and Alphabet accounting for approximately two-thirds of the total (35% and 31%, respectively).
Three hyperscalers—Alphabet, Meta and Oracle—have also turned to equity markets for the first time since 2013, raising $162 billion year to date (excluding Meta’s additional $60 billion at-the-market programme planned for Q1 2027).
Exhibit 2: Debt Financing for three cohorts ($ billions)
Source: LSEG Workspace, Gross Bond Issuance & Proceeds. Past performance is not a guide to future returns. Please see the end for important legal disclosures.
| Period | Hyperscalers (USD bn) | Neoclouds (USD bn) | AI infrastructure (USD bn) |
|---|---|---|---|
| 2015–2024 annual average | 25.5 | 0.5 | 2.4 |
| 2025 | 108.1 | 3.8 | 0.0 |
| 2026 YTD | 279.0 | 6.3 | 2.1 |
Exhibit 3: Equity Financing for three cohorts ($ billions)
| Period | Hyperscalers (USD bn) | Neoclouds (USD bn) | AI infrastructure (USD bn) |
|---|---|---|---|
| 2015–2024 cumulative | 0.0 | 4.7 | 29.6 |
| 2025 | 0.0 | 23.0 | 3.7 |
| 2026 YTD | 162.4 | 27.3 | 14.1 |
Hyperscalers outperform on return on capital
Despite growing financing needs, hyperscalers remain better positioned to attract capital, supported by their ability to generate returns on invested capital (ROIC) above their weighted average cost of capital (WACC). Exhibit 4 helps explain why investors remain willing to finance hyperscaler expansion despite elevated capex intensity. This cohort sits in the top left quadrant, led by Alphabet, Microsoft and Meta who generate the highest ROIC-WACC spreads over the next twelve months. In contrast, neoclouds cluster in the bottom-right quadrant with negative ROIC-WACC spreads.
The divergence between hyperscalers and neoclouds is also reflected in their cost of capital. Hyperscaler WACC has risen from approximately 7% in early 2025 to 9% today, while individual neoclouds and AI infrastructure companies face WACCs ranging from 10% to 20%. Higher WACCs raise the hurdle for future investments as all three cohorts increasingly rely on external financing, placing greater scrutiny on the returns from AI spending.
Exhibit 4: Capex Intensity vs. ROIC-WACC Spread
Source: LSEG Workspace. LSEG StarMine. Past performance is not a guide to future returns. Please see the end for important legal disclosures.
| Company | Cohort | NTM capex / CFO | NTM ROIC-WACC spread |
|---|---|---|---|
| GOOGL | Hyperscalers | ~105% | ~45% |
| MSFT | Hyperscalers | ~80% | ~17% |
| META | Hyperscalers | ~115% | ~12% |
| AMZN | Hyperscalers | ~90% | ~3% |
| BABA | Hyperscalers | ~105% | ~1% |
| ORCL | Hyperscalers | ~130% | ~2% |
| EQIX | AI infrastructure | ~105% | ~-5% |
| DLR | AI infrastructure | ~145% | ~-4% |
| CRWV | Neoclouds | ~225% | ~-7% |
| IREN | Neoclouds | ~535% | ~-35% |
| NBIS | Neoclouds | ~545% | ~-5% |
Earning quality, short interest, and credit risk
The warning signs emerging throughout this fundamental analysis are equally visible through a quantitative lens. StarMine models capture many of these underlying pressures, from deteriorating earnings quality and rising short interest to heightened credit risk across the AI ecosystem as shown in Exhibit 5.
It can be observed that earnings quality (EQ) scores have generally declined among hyperscalers, consistent with growing pressure on FCF. All six hyperscalers have EQ scores below 50 on a scale of 1 to 100 (with 100 being best), with Amazon, Oracle and Alibaba ranking in the bottom decile.
Further, elevated short interest levels suggest that investors are taking more bearish positions in neoclouds and AI infrastructure companies. Short interest is particularly high for TeraWulf (25.7%), Core Scientific (23.8%), IREN (23.4%), Cipher Digital (22.1%), and Applied Digital (21.7%), compared with 4.2% for the median Russell 1000 company.
Finally, Credit risk indicators also point to greater financial vulnerability among neoclouds and AI infrastructure companies. Estimated 12-month probabilities of default are highest for Cipher Digital (8.0%), Hut 8 (4.3%), CoreWeave (4.1%), Applied Digital (2.4%), and WhiteFiber (2.3%).
Exhibit 5: StarMine Model Scores
Source: LSEG Workspace. LSEG StarMine. Past performance is not a guide to future returns. Please see the end for important legal disclosures.
| Company | Cohort | NTM capex / CFO | NTM ROIC-WACC spread |
|---|---|---|---|
| GOOGL | Hyperscalers | ~105% | ~45% |
| MSFT | Hyperscalers | ~80% | ~17% |
| META | Hyperscalers | ~115% | ~12% |
| AMZN | Hyperscalers | ~90% | ~3% |
| BABA | Hyperscalers | ~105% | ~1% |
| ORCL | Hyperscalers | ~130% | ~2% |
| EQIX | AI infrastructure | ~105% | ~-5% |
| DLR | AI infrastructure | ~145% | ~-4% |
| CRWV | Neoclouds | ~225% | ~-7% |
| IREN | Neoclouds | ~535% | ~-35% |
| NBIS | Neoclouds | ~545% | ~-5% |
To summarise, we find that hyperscalers retain stronger balance sheets and returns on capital, while neoclouds and AI infrastructure companies are making a larger bet on future growth to justify today's investment. The question for investors is how long they are willing to look past deteriorating near-term fundamentals in anticipation of longer-term AI returns, particularly given the risk of excess capacity if demand falls short of expectations . Ultimately, the sustainability of this investment cycle will depend on whether AI monetisation can translate into sufficient cash generation and returns above the cost of capital.
Securitisation has grown rapidly into a major funding source via ABS and CMBS
As AI-driven computing buildout booms, securitisation has grown rapidly into a major funding source complementing bank debt, private credit, and corporate bonds. Data centre financing through the securitisation market allows operators to convert predictable lease cash flows and physical real estate asset s into tradable securities of varying duration and credit ratings for fixed income investors. Data centre projects generally begin with bank construction loans, private credit, or corporate debt, and transition to securitisation financing only after the fa cility is built, generating steady long-term lease cash flows.
There are two primary vehicles of data centre securitisation:
- Asset-Backed Securities (ABS): Backed directly by lease revenue and operating cash flow of a portfolio of data centre facilities through a revolving master trust structure. Master trusts are scalable, allowing dynamic collateral pools of contractual receivables and flexibility for operators/sponsors to add collateral and issue more debt over time.
- Commercial Mortgage-Backed Securities (CMBS): Backed by commercial real estate mortgage loans secured by the underlying data centre properties, typically structured as single -asset, single-borrower (SASB) transactions with a fixed/static collateral pool. Security cash flows are derived from mortgage debt payments made by the property owner.
Given that the facilities through securitisation financing are typically completed and leased out, they generally would have limited exposure to potential regulatory changes following the post midterm election (unlike those still in planning or being built). As new projects halt, construction costs rise, and timelines extend due to increased regulatory friction, a slower data centre supply pipeline can potentially strengthen the fundamentals of those already in op eration.
For investors, the central question is cash flow durability and the long-term value of the data centre assets. A data centre's earning potential depends primarily on usable power capacity, together with fibre connectivity, cooling, and system redundancy. Given the risks with property depreciation rates and residual values being hard to predict, asset analysis must assess both current operating capabilities and the future capital spending needed to upgrade hardware and technology.
With issuance rising sharply since 2025
Exhibit 6: ABS and CMBS Data Centre Issuance
Source: Green Street, LSEG Yield Book (November 2026). Past performance is not a guide to future returns. Please see the end for important legal disclosures.
| Year | Data centre ABS ($m) | Data centre CMBS ($m) |
|---|---|---|
| 2020 | 2,380* | ~800 |
| 2021 | ~6,500 | ~3,200 |
| 2022 | ~1,200 | ~2,800 |
| 2023 | ~6,200 | ~2,800 |
| 2024 | ~8,600 | ~3,600 |
| 2025 | 15,700* | ~12,500 |
| YTD 2026 | 15,320* | ~6,500 |
U.S. data-centre ABS has risen significantly since 2020 with a total of 90 transactions and $55.96 billion of issuance. Annual data-centre issuance increased from $2.38 billion in 2020 to $15.70 billion in 2025. year to date 2026, 20 data -centre transactions generated $15.32 billion of issuance, almost matching the full-year 2025 volume.
The growing popularity of ABS securitisation for data centre financing is driven by the appeal of the ABS master-trust financing structure and the need for repeat access to capital as operators expand their platforms. Furthermore, the SEC recently ruled that qualifying data centre ABS securitizations are not considered "asset-backed securities" under Section 3(a)(79) of the Securities Exchange Act so they can avoid rigid Exchange Act ABS boxes such as standard Regulation AB disclosures and risk-retention mandates.
Meanwhile, from 2020 through October 2026, U.S. data centres supported 28 CMBS transactions with a total issuance volume of $31.96 billion. Issuance has accelerated in 2025 and year to date 2026, totalling $19.02 billion, or approximately 60% of all data-centre CMBS volume since 2020. The average size of data-centre CMBS transactions was $1.14 billion, larger than that of data-centre ABS transactions of $622 million, as we found larger-capacity facilities are more prevalent in CMBS deals.
Blackstone is by far the largest sponsor of data centre CMBS deals. Blackstone-associated borrowers accounted for 15 of 28 deals and $21.98 billion of issuance, representing 53.6% of deal count and 68.8% of volume. Blackstone's volume share was 71.1% in 2025 and 50.6% in year to date 2026.
Credit quality of CMBS data centre loans seem to be slightly weaker than non-data centre loans. Across all vintages, data-centre loans had a weighted average LTV of 65.5%, versus 64.3% for non-data-centre CMBS loans, while the Debt Service Coverage Ratio (DSCR) was lower at 1.83x versus 1.99x. That said, credit performance has held up so far as none of the data centre loans has been delinquent.
But spreads gapped out amid AI concerns…
Exhibit 7: ABS and CMBS Data Centre New Issue Spreads
Source: Green Street, LSEG Yield Book (November). Past performance is not a guide to future returns. Please see the end for important legal disclosures.
| Period | ABS A- spread (bp) | CMBS AAA spread (bp) |
|---|---|---|
| Q1 2025 | ~185 | ~150 |
| Q2 2025 | ~183 | ~130 |
| Q3 2025 | ~168 | ~172 |
| Q4 2025 | ~212 | ~170 |
| Q1 2026 | ~209 | ~170 |
| Q2 2026 | ~192 | ~140 |
| Q3 2026 | ~225 | ~188 |
| Q4 2026 YTD | ~274 | Not shown |
Nonetheless, data-centre securitisation new-issue spreads widened out significantly in recent months, as ABS A- bond spreads widened by 82 bps from the second quarter of 2026 to the fourth quarter of 2026, and CMBS AAA bond spreads widened by 42 bps from the second quarter of 2026 to the third quarter of 2026 (no CMBS data centre deals issued in the fourth quarter of 2026 so far).
Exhibit 8: Data Centre CMBS AAA Market Spreads Movement from YE2025 to Oct 2026
| Data Centre CMBS AAA Market Spreads Movement from YE2025 to Oct 2026 | ||||
|---|---|---|---|---|
| Deal Name | Rate Type | 2025 Year-End AAA Spread (bp) |
2026 Oct AAA Spread (bp) |
Change (bp) |
| VDCM 2025-AZ | Fixed | 73.1 | 162.6 | +89.5 |
| DC 2023-DC | Fixed | 96.8 | 148.7 | +51.9 |
| JPMCC 2022-DATA | Fixed | 117.7 | 169.4 | +51.6 |
| BX 2024-VLT5 | Fixed | 122.9 | 173.4 | +50.5 |
| DATA 2023-CNTR | Fixed | 128.4 | 174.1 | +45.7 |
| DATA 2024-CTR2 | Fixed | 120.1 | 122.7 | +2.7 |
| CONE 2024-DFW1 | Floating | 169.2 | 214.6 | +45.5 |
| SWCH 2025-DATA | Floating | 172.7 | 211.7 | +39.0 |
| BX 2024-VLT4 | Floating | 157.2 | 186.2 | +29.0 |
| BX 2025-VLT7 | Floating | 171.2 | 197.6 | +26.4 |
| BX 2025-VOLT | Floating | 173.1 | 197.9 | +24.8 |
| BX 2025-COPT | Floating | 171.9 | 186.3 | +14.4 |
| BX 2022-IND | Floating | 141.8 | 149.1 | +7.3 |
| BX 2025-SPOT | Floating | 144.0 | 147.1 | +3.1 |
| BX 2025-VLT6 | Floating | 177.7 | 179.9 | +2.2 |
| Average | All | 142.5 | 174.8 | +32.2 |
Source: LSEG Pricing Service, LSEG Yield Book (November 2026). Past performance is not a guide to future returns. Please see the end for important legal disclosures.
Focusing on market spreads movement of data centre CMBS AAA bonds from year-end 2025 through October 2026, the widening was broad-based with all six fixed-rate and nine floating-rate deals experiencing spread increases (average widening of 32 bps, with 49 bp for fixed-rate and 21 bp for floating-rate). VDCM 2025-AZ Class A posted the largest widening among fixed-rate bonds at 89.5 bp. Among floating-rate bonds, CONE 2024-DFW1 Class A saw the largest widening at 45.5 bp.
…Even if there is still limited available data centre capacity & strong leasing demand
The data centre security spreads widening is notable against a backdrop of strong leasing demand and limited available data-centre capacity. It was driven by broad AI spending concern especially hyperscalers' capital expenditure pressures, reflecting deterioration in capital market sentiment rather than fundamental weakness in the asset class. Nevertheless, there could be more scrutiny on tenant and platform concentration, tenant creditworthiness, lease expirations/ renewal assumptions, termination rights, operating-cost allocations, reliability of service delivery, and the potential for higher capital expenditures, as those factors can drive the differentiation of spread performance across data centre securitizations.
Will the growth continue?
Following the recent sharp AI stock selloff, banks and credit investors are becoming increasingly wary about financing AI buildouts. Credit standards of lending could be tightening, and investors may step up cash flow and contractual risk scrutiny. Borrowing cost is poised to rise on Fed rate hike outlook and debt spread widening.
Despite weakening sentiment and growing pressure on riskier borrowers such as neocloud operators, the sector's substantial funding needs may persist given the current compute demand and the resilient balance sheet of hyperscalers. While a near-term slowdown in the pace of AI buildout is likely, partly reflecting regulartory uncertainty following the midtemr elections, it remains to be seen whether the data centre financing market can stabilise and continue to expand as the AI theme keep s evolving.
Footnotes
[1] US SIFMA data to end-Q3, 2026. | Back to Note 1
[2] US Congressional Budget Office estimate, October 2026. | Back to Note 2
[3] US Bureau of Economic Analysis estimate, October 2026. | Back to Note 3
Legal Disclaimer
Republication or redistribution of LSE Group content is prohibited without our prior written consent.
The content of this publication is for informational purposes only and has no legal effect, does not form part of any contract, does not, and does not seek to constitute advice of any nature and no reliance should be placed upon statements contained herein. Whilst reasonable efforts have been taken to ensure that the contents of this publication are accurate and reliable, LSE Group does not guarantee that this document is free from errors or omissions; therefore, you may not rely upon the content of this document under any circumstances and you should seek your own independent legal, investment, tax and other advice. Neither We nor our affiliates shall be liable for any errors, inaccuracies or delays in the publication or any other content, or for any actions taken by you in reliance thereon.
Copyright © 2026 London Stock Exchange Group. All rights reserved.
The content of this publication is provided by London Stock Exchange Group plc, its applicable group undertakings and/or its affiliates or licensors (the “LSE Group” or “We”) exclusively.
Neither We nor our affiliates guarantee the accuracy of or endorse the views or opinions given by any third party content provider, advertiser, sponsor or other user. We may link to, reference, or promote websites, applications and/or services from third parties. You agree that We are not responsible for, and do not control such non-LSE Group websites, applications or services.
The content of this publication is for informational purposes only. All information and data contained in this publication is obtained by LSE Group from sources believed by it to be accurate and reliable. Because of the possibility of human and mechanical error as well as other factors, however, such information and data are provided "as is" without warranty of any kind. You understand and agree that this publication does not, and does not seek to, constitute advice of any nature. You may not rely upon the content of this document under any circumstances and should seek your own independent legal, tax or investment advice or opinion regarding the suitability, value or profitability of any particular security, portfolio or investment strategy. Neither We nor our affiliates shall be liable for any errors, inaccuracies or delays in the publication or any other content, or for any actions taken by you in reliance thereon. You expressly agree that your use of the publication and its content is at your sole risk.
To the fullest extent permitted by applicable law, LSE Group, expressly disclaims any representation or warranties, express or implied, including, without limitation, any representations or warranties of performance, merchantability, fitness for a particular purpose, accuracy, completeness, reliability and non-infringement. LSE Group, its subsidiaries, its affiliates and their respective shareholders, directors, officers employees, agents, advertisers, content providers and licensors (collectively referred to as the “LSE Group Parties”) disclaim all responsibility for any loss, liability or damage of any kind resulting from or related to access, use or the unavailability of the publication (or any part of it); and none of the LSE Group Parties will be liable (jointly or severally) to you for any direct, indirect, consequential, special, incidental, punitive or exemplary damages, howsoever arising, even if any member of the LSE Group Parties are advised in advance of the possibility of such damages or could have foreseen any such damages arising or resulting from the use of, or inability to use, the information contained in the publication. For the avoidance of doubt, the LSE Group Parties shall have no liability for any losses, claims, demands, actions, proceedings, damages, costs or expenses arising out of, or in any way connected with, the information contained in this document.
LSE Group is the owner of various intellectual property rights ("IPR”), including but not limited to, numerous trademarks that are used to identify, advertise, and promote LSE Group products, services and activities. Nothing contained herein should be construed as granting any licence or right to use any of the trademarks or any other LSE Group IPR for any purpose whatsoever without the written permission or applicable licence terms.